ASSOCIATED GAS RE-INJECTION

Section 1: Duty to submit preliminary programme for gas re-injection.

1979Section 1 of 8Federal Republic of Nigeria

Notwithstanding the provisions of regulation 42 of the Petroleum (Drilling and Production) Regulations made under the Petroleum Act, every company producing oil and gas in Nigeria, shall not later than 1 April, 1980 submit to the Minister a preliminary programme for-
(a) schemes for the viable utilisation of all associated gas produced from a field or groups of fields;
(b) project or projects to re-inject all gas produced in association with oil but not utilised in an industrial project.

Cite this section

Section 1, ASSOCIATED GAS RE-INJECTION (1979).

https://repo.podus.ai/laws/associated-gas-re-injection/section/1/