(1) Subject to such terms and conditions as the Commission may fix in the licence, a transmission licence shall authorise the licensee to carry on grid construction, operation, and maintenance of transmission system within Nigeria, or that connect Nigeria with a neighbouring jurisdiction.
(2) The transmission licensee that is a successor company formed under section 8 may also have an obligation to carry out system operation, including the procurement of ancillary services, pursuant to the terms of a system operation licence issued by the Commission to such licensee.