ELECTRIC POWER SECTOR REFORM ACT

Section 50: Rehearing and Appeals.

2005Section 50 of 101Federal Republic of Nigeria

(1) Subject to this section, any person who is aggrieved by :
(a) a decision of the Commission not to issue a licence;
(b) any term or condition of a licence issued to him, or a refusal by the Commission to specify, a term or condition in a licence;
(c) a refusal by the Commission to renew a licence;
(d) any amendment of a licence or a refusal by the Commission to amend a licence;
(e) the cancellation of a licence;
(f) the grant or refusal by the Commission to grant any approval or authority in terms of this Act ;
(g) the outcome of any arbitration or mediation by the Commission of a dispute between licensees;
(h) a decision of the Commission with respect to prices or tariffs;
(i) any other decision of the Commission; may apply to the Commission for review of the decision, order or refusal.
(2) The Commission may, reconsider, vary or rescind its decisions before issuing a final decision, in accordance with such procedures as the Commission may establish; provided that such review or reconsideration shall be completed within sixty days of the date it is requested.

Cite this section

Section 50, ELECTRIC POWER SECTOR REFORM ACT (2005).

https://repo.podus.ai/laws/electric-power-sector-reform-act/section/50/